The Project Feasibility Study (FS) is a preliminary study to be conducted by every Property Developer involved in Housing Development in Malaysia. It's also famous known as FS.



PROCESS TO PRODUCE FEASIBILITY STUDY
Factors to be considered in preparing FS.

1. Land Area.
It is important to know the size and shape of the land. The size and will affect the development component to be developed on that land.

 2. Topography.
The topography will be appeared when the land surveyor produce the Contour Plan. It will capture the highest level and lowest level of the land. 


3. Density
In general it is determined by the planning requirements by respective local authority.

4. Layout Plan
It is paramount to have, highest and best use of layout plan, in order to maximise Gross Development Value (GDV). 

5. Market Study
It will determine type of product to be considered in the proposed development. In addition market study also to advice on the proposed sale value by considering the competitor product and market value.

6. Infrastructure cost
Infra cost for the whole project is vital, to reflect the cost to be shared by every products listed in the FS.

7. Building cost
The cost to be calculated based on construction cost psf, 

8. Land cost
The cost to be considered is the market value of the land. 

9. Professional fees
The cost to pay the appointed consultants from the very beginning until project completion.
It consists of several components that must be included in the study as follows: 


Project Feasibility Study

Main Component

1. Gross Development Value (GDV)
2. Gross Development (GDC)
3. Infrastructure Cost 
4. Land Cost
5. Professional fees
6. Contribution to Local Authorities
7. Overheads
8. Profit BeforeTax(PBT)
9. Return on Cost(ROC)



1.0 Gross Development Value (GDV)

GDV is the total value of the proposed development project. It includes residential units, commercial units, industrial lots and vacant land.

GDV is calculated based on the type of product and the proposed selling price.

Sample of GDV calculation :

Type of Development
Total Unit
Land Area
Built up area (sf)
Selling Price (psf)
Selling Price /Unit
Total GDV







Single Storey Terrace (20’x 50’)
10
20’x70’
1,000
150.00
150,000
1,500,000.00
Double Storey Terrace (24’x 60’)
10
24’x 80’
2,500
200.00
500,000
5,000,000.00







Total
20




6,500,000.00

Based on the above sample, the total GDV is RM6,500,000.

2.0 Gross Development Cost (GDC)

GDC is the total cost of the proposed development project.

 The cost involved is as follows:


i. Building cost
ii.Infrastructure cost
iii.Land Cost
iv.Professional Fees
v.Contribution to Local Authorities
vi.Marketing Fees
vii.Other cost

Sample of GDC calculation :

Type of Development
Total Unit
Land Area
Built up area (sf)
Selling Price (psf)
Selling Price /Unit
Total GDV







1.0 BUILDING COST






Single Storey Terrace (20’x 50’)
10
20’x70’
1,000
150.00
150,000
1,500,000.00
Double Storey Terrace (24’x 60’)
10
24’x 80’
2,500
200.00
500,000
5,000,000.00
Proff fees (Building) 






Legal Fees (SPA) 







2.0 DIRECT PROJECT COST  






Local Infrastructure cost 





2,000,000
Professional Fees   (3%)
Sales & Marketing Cost (10%)
Contingency (10%)

3.0 LAND COST
Land Value

4.0 COMMON PROJECT COST
Government Charges
Major Infrastructure Cost
Proff fees (General)
Property Management Cost
Sale & Marketing cost (township)
Financial Interest
Contingencies

5.0 OVERHEADS
Administrative and Project Management

6.0 TOTAL DEVELOPMENT COST
To Add items (1.0 to 5.0)





60,000







Total








The failure of FS will contribute to the following factor:

1. Low take up-rate
The proposed product (land size, built-up area, selling price) is far below expectation of the potential purchaser.

2. Low Return on Investment (ROI)
Inaccurate estimating for construction and other cost will led to low ROI.














10 comments:

  1. subjek apa yang kita akan belajar dalam dip in building ni ya? tq

    ReplyDelete
  2. Bldg services, bldg maintenance dll

    ReplyDelete
  3. Excellent information on your blog,Building surveys thank you for taking the time to share with us. Amazing insight you have on this, it's nice to find a website that details so much information about different artists.

    ReplyDelete
    Replies
    1. FS will be used by Malaysia Property Developer before they embark on any new prop development. All proposed selling price ( Gross Development Value) will be pre determined in relation to Gross Development Cost.

      Delete
  4. FS will be used by Malaysia Property Developer before they embark on any new prop development.Aluminium Scaffolding


    ReplyDelete
  5. Very informative Blog.Thank you for Sharing this.I Know how Much Feasibility Study is important for Business.

    ReplyDelete
    Replies
    1. TQ Priya, FS is vital for any biz. In property development the proposed FS should be able to reflect the real situation of current market.

      Delete
  6. Such a nice blog, I want to say thank you for sharing very informative blog. i read your full article its have very different strategy for building inspection. its very important thing to know about building inspection for more details please Building inspection sydney

    ReplyDelete
  7. This is a really informative knowledge, Thanks for posting this informative Information. Building inspection sydney

    ReplyDelete
  8. how i want to know how the project management cost determined

    ReplyDelete